Pavement Management Program

2015 Construction Schedule

(Last Update- May 15th, 2015)

Below is a list of neighborhoods where the City will be paving this year. A schedule is being developed and work is anticipated to begin soon.  Between all of the locations there is over seven miles of pavement scheduled for resurfacing this year.  We anticipate that the whole project will be ongoing through October, though each neighborhood will only be impacted for a short duration.

As work gets closer in each neighborhood, the contractor will be posting no parking signs. The time restrictions for parking are typically 7:00 am to 5:00 pm, Monday through Friday.

Planned Work: Pavement Overlay

Sites

Location/Neighborhood

Work to be done

1

THE CREST ON THE PLATEAU

Pavement Overlay

2

MONTAGE

Pavement Overlay

3

236TH AVE SE
PINE HILL
CLAREMONT

Pavement Overlay

4

HIGH COUNTRY

Pavement Overlay

5

TIBBETS STATION

Pavement Overlay

6

EAGLE RIDGE
ALEXANDER'S ON THE LAKE
PEREGRINE POINT

Pavement Overlay
Underdrains
ADA Ramps

7

CAMBRIA

Pavement Overlay
Underdrain

8

ISSAQUAH BEAVER LAKE RD

Pavement Overlay
ADA Ramps
            Pathway Improvement near 256th Ave SE

9

DUTHIE HILL RD

Pavement Overlay


































General Information about the Project:

Hours of work will be between 7:00 am and 5:00pm  daily.

Driveway Access
on most streets will remain open throughout most of the construction but traffic will be reduced to sharing a lane controlled by flaggers. In cul-de-sacs, crews will work with the residents to temporarily close the cul-de-sac so that paving operations can be completed quickly. During the actual paving process, there is typically a two to three hour time period where access to driveways is not allowed. This is time needed for the pavement to cool and harden before traffic can drive on it.

On Street Parking on the days of construction, on-street parking will need to be restricted. Signs will be posted in advance of the work to notify residents of the parking restrictions.

Waste and Recycling Schedule is not changed due to construction. When days of paving and waste collection coincide, we work with the collection service to adjust their route schedule and focus first on the streets that are being paved. If there is construction in your neighborhood, please be sure to have your waste and recycling out extra early.

Tree Trimming may need to be done in front of your house. If there is vegetation in front of your property that extends out into the street, it will need to be pruned back to allow the equipment to do the street resurfacing. Please trim the vegetation along your property if this is the case. City crews or the Contractor will trim vegetation as needed for the project. However, they will only be doing the minimum needed to clear the road for paving and some additional trimming may need to be completed afterwards by the adjacent property owner.

Street Cuts - Ordinance # 02001-78 prohibits the excavation of resurfaced or newly constructed roads for a minimum of five years following construction or paving. If you are planning to have any underground utility work done, such as water, sewer, telephone, gas, electrical, etc., you are strongly encouraged to expedite this work if it involves utility work under the new pavement. Please call us as soon as possible to coordinate this work.

If you have any questions about the construction please call or email Jim Grueber.

Staff Contact

Jim Grueber                                    Derya Dilmen     
W: (425) 295-0566                     W: (425) 295-0574
C:  (425) 445-9037                          

 jgrueber@sammamish.us           ddilmen@sammamish.us

Resources