Loading
select
< November 2014 >
S M T W Th F S
      1
2345678
9101112131415
16171819202122
23242526272829
30      

Pavement Management Program

2014 Construction Schedule

(Updated July 24th)

Below is a list of neighborhoods where the City will be paving this year. The order of neighborhoods below is the anticipated progress for work by the Contractor.  This may change as there is coordination with other projects that needs to be done.

As work gets closer in each neighborhood, the contractor will be posting no parking signs. The time restrictions for parking are typically 7:00 am to 5:00 pm, Monday through Friday.

Current Work:
Kempton Downs &  Lacraint - utility adjustments

Heritage Hills - pavement striping

Next Site: Trossachs Blvd

Anticipated Start Date

Location/Neighborhood

Remaining Work

 05/27/2014

 Sammamish Wood Highlands

 Complete

 05/27/2014

 Loree Estates

 Complete

 06/04/2014

 Pine Lake Heights

 Complete

 06/27/2014

 Heritage Hills

 Pavement striping

 07/14/2014

 Kempton Downs

 Utility Adjustments

 07/14/2014

 Lacraint

 Utility Adjustments

 08/11/2014

 Trossachs Blvd

 

 Uplands

 SE 48th St

General Information:

Hours of work will be between 7:00 am and 5:00pm  daily.

Driveway Access on most streets will remain open throughout most of the construction but traffic will be reduced to sharing a lane controlled by flaggers. In cul-de-sacs, crews will work with the residents to temporarily close the cul-de-sac so that paving operations can be completed quickly. During the actual paving process, there is typically a two to three hour time period where access to driveways is not allowed. This is time needed for the pavement to cool and harden before traffic can drive on it.

On Street Parking on the days of construction, on-street parking will need to be restricted. Signs will be posted in advance of the work to notify residents of the parking restrictions.

Waste and Recycling Schedule is not changed due to construction. When days of paving and waste collection coincide, we work with the collection service to adjust their route schedule and focus first on the streets that are being paved. If there is construction in your neighborhood, please be sure to have your waste and recycling out extra early.

Tree Trimming may need to be done in front of your house. If there is vegetation in front of your property that extends out into the street, it will need to be pruned back to allow the equipment to do the street resurfacing. Please trim the vegetation along your property if this is the case. City crews or the Contractor will trim vegetation as needed for the project. However, they will only be doing the minimum needed to clear the road for paving and some additional trimming may need to be completed afterwards by the adjacent property owner.

Street Cuts - Ordinance # 02001-78 prohibits the excavation of resurfaced or newly constructed roads for a minimum of five years following construction or paving. If you are planning to have any underground utility work done, such as water, sewer, telephone, gas, electrical, etc., you are strongly encouraged to expedite this work if it involves utility work under the new pavement. Please call us as soon as possible to coordinate this work.

If you have any questions about the construction please call or email Jim Grueber.

Staff Contact

Jim Grueber
W: (425) 295-0566
C: (425) 445-9037
 jgrueber@sammamish.us

Resources