Timeline

Master Plan to Phased Construction

Public Meetings June - September 2007
Park Commission Updates June 2007 - December 2008
City Council Updates June 2007 - December 2008
Master Plan Adoption September 2009
Phase I Construction Documents Fall 2010
Phase I Permitting Winter 2010/2011
Phase I Bid Spring 2011
Phase I Construction Summer 2011
Park Opening Fall 2011
On-Going Volunteer Work Parties and Partnerships January - December 2012
Phase II Design and Construction Documents January - December 2013
Phase II Permitting January - February 2014
Phase II Bid (parking lot improvements) April 2014
Phase II Construction April/May 2014 - August 2014
Sahalee Parking Lot and Trail Connection Opening August 1, 2014