Timeline
Master Plan to Present
Master Plan |
July 2008 to July 2010 |
Phase I Design |
Winter 2010 to Spring 2011 |
Phase I Construction Documents |
Spring 2011 |
Phase I Construction (except docks) |
Summer/Fall 2011 |
Phase I Dock Construction |
October 2012 to March 2013 |
Phase II Design, Permitting, Construction Documents |
January to July 2014 |
Phase II Partial Construction |
September 2014 to February 2015 |
ADA Access Improvements Design, Engineering, Construction Documents |
September 2016 to March 2017 |
ADA Access Improvements Bid, Award |
April 2017 to May 2017 |
ADA Access Improvements Construction
|
June 2017 to September 2017
|