Louis Thompson Hill Road Slope Repair

Summary

This project will design a new wall to repair slope damage below Louis Thompson Hill Road at 210th Place SE. A new culvert will be constructed across the road.

Project Updates

Seeking Council authorization on May 2nd to begin design.

Goals and Benefits

This project will repair slope damage and prevent undermining of the roadway at the existing retaining wall. The stormdrain modifications will help address the flooding and erosion that caused the washouts, and prevent erosion into upper Zackuse Creek.

Timeline

Construction is planned to begin Spring 2018.

Budget

$900,000 (planning level estimate)

Permits, Environmental Review

Applications will be made for SEPA and an HPA permit from Washington Department of Fish and Wildlife to restore the stream buffer.

Staff Contact