2017 Curb Ramp Retrofit and Sidewalk

2017 Curb Ramp Retrofit and Sidewalk Repair Construction Schedule:

Location/Neighborhood 

Work to be done

Site 1: TIMBERLINE

Concrete Work Completed

**Sodding has not be completed at all locations within Timberline.  Contractor will be jumping back to finish.

Site 2: NE 22ND ST

Changed - Completed


Site 3: SUMMER RIDGE

Concrete Work Completed

Site closeout items (including sod, topsoil and paving ongoing)


Site 4: SUFFIELD

Concrete Work Completed

Site closeout items (including sod, topsoil and paving ongoing)

Site 7: PINE ACRES

Currently working on 213th Pl SE and 214th Pl SE.

Ramp removal and concrete pouring will begin on 217th Ave SE and 218th Ave SE within the next.

Ramps on 218th: Due to the existing sidewalk not having a curb, the pavement thickened edge will act as the curb during the installation of the ramps.

Site 8: KLAHANIE

Concrete Work Completed

Site closeout items (including sod, topsoil and paving ongoing)



General Information about the Project:

Hours of work will be between 7:00 am and 5:00pm  daily. 

Driveway Access
 on most streets will remain open throughout most of the construction.

Street parking may be hindered around areas where curb ramps, sidewalks and curbs will be retrofitted.  Signs will be posted in advance of the work to notify residents of the parking restrictions.

Waste and Recycling Schedule is not changed due to construction.

Tree Trimming and plant removal may need to be done in front of your house. If there is vegetation in front of your property that extends withing two feet of the sidewalk, it will need to be pruned back to allow the equipment to excavate and pour concrete. Please trim the vegetation along your property if this is the case. City crews or the Contractor will trim vegetation as needed for the project. However, they will only be doing the minimum needed to clear the road for sidewalk/curb and some additional trimming may need to be completed afterwards by the adjacent property owner.


The project has been advertised at Builders Exchange http://www.bxwa.com
The bid due date was 4/6/2017.

The work dates listed are subject to change due to weather, equipment and occasional scheduling conflicts.

The contractors will be back to install sod behind ramps/sidewalk where grass existed.  The City decided to allow the contractors to wait on installing the sod until the wetter season began.

Updated: BR 09.20.17

Staff Contact