2020 Curb Ramp Retrofit and Sidewalk Repair Project

Post-Concrete Pour.JPG

OVERVIEW

Curb ramp retrofits and sidewalk repairs are a critical component of maintaining our current roadway network.  Per the ADA laws that went into effect in 2009, all street crossings with an overlay that crosses an intersection must improve all curb ramps to meet the current standards specified in the Americans with Disabilities Act.  This project is designed to update all crossings before we overlay our streets.  This project also incorporates additional cracked sidewalks throughout the City that are deemed potential hazards, but are outside of the scope of our Maintenance Department's traditional repairs.

The work dates listed are subject to change due to weather, equipment and occasional scheduling conflicts with other regional paving work.

2020 Curb Ramp Retrofit and sidewalk repair MAP

Location/Neighborhood 

Site Specific Work Schedules

Site 1: Heritage Hills

-Sawcutting August 19/20th
-Removal begins around September 8th

Site 2: Deer Park

TBD

Site 3: Autumn Wind

-Sawcutting August 19/20th
-Removal begins around September 14th

Site 5: 228th Ave SE

Finished

Site 7: SE 24th Way

-Sawcutting August 19/20th
-Removal October, 2020

Site 8: East Beaver Lake Drive

-Removal begins around August 31st

Site 9: Livingston and Hunter's Ridge

Current Construction. Finishing week of August 31st

 

 

PROJECT TIMELINE

Design Completed: February 26, 2020
Advertised for bidding: February 27, 2020
Bid Opening: March 12, 2020
Award Project: March 17, 2020
Preconstruction Meeting: April 30, 2020
Begin Construction/NTP: May 12, 2020
Estimated Project Completion: October, 2020

 PROJECT CONTRACT TOTAL

RRJ Company, LLC
$1,102,729.21

PROJECT PROGRESS

45.5% Completed
Payment 1: $78,514.06
Payment 2: $229,278.59
Payment 3: $194,494.94

PROJECT BIDDING

The project has been advertised at Builders Exchange http://www.bxwa.com.  A Notice to Contractors was posted in the Daily Journal and Seattle times on February 27th and March 5th, 2020.

Bids were opened on March 12th, 2020 at 10:00am.  The City received 5 bids:
1. RRJ Company, LLC - $1,102,729.21
2. Westwater Construction - $1,192,147.00
3. Nordvind - $1,219,717.50
4. Transportation Systems - $1,289,680.00
5. RL Alia - $1,321,684.00

2020 Curb Ramp Retrofit Bid Tab

Updated: BR 08.28.20

Staff Contact