2018 Pavement Overlay Schedule

2018 Construction Schedule:

Location/Neighborhood 

Work to be done

Site 1: East Lake Sammamish Parkway                  

To: Sammamish Landing
From: Northern City Limit

Updates Coming Soon

Site 2: NE 37th Way

To: Sahalee Way NE
From: 205th Pl NE

Updates Coming Soon - Expected 4th Paving Site

Site 3: 205th Pl NE

To: NE 33rd Ct
From: NE 19th Pl

Updates Coming Soon - Expected 5th Paving Site

Site 4: Inglewood Div. I & II, Lincolnshire and Sahalee South Plats                                                                                                

SITE MAP

Inglewood Div I & II, Lincolnshire and the Sahalee South are the first areas that will be overlaid this year.  Crews posted door hangers, put up 'No Parking' signs and began prepping the site for the Overlay on June 7th.

Schedule:
Site preparation will continue through the week of June 11th.  This includes trimming limbs, exposing pavement edges, and cleaning the pavement surface.

Grinding will begin June 12th and will continue through June 14th.

Patching will begin June 14th and are located within the areas marked out in White Paint.

CHANGE: It does not appear that there will be any paving until the week of July 2nd. (BR 6/21)

Site 5: Sunny Hills (SE 30th St & 245th Ave SE)

To: 252nd Ave SE
From: 244th Ave SE

Crews will post door hangers and begin putting up 'No Parking' signs on June 21st'No Parking' signs cannot be enforced until June 25th.

Schedule:
Site Preparation will begin on June 22nd.

Grinding is anticipated to begin the week of June 25th.  This will include driveway edge grinding, planing and patching.

Unknown when paving will begin.

Site 6: 228th Ave SE

To: Southern City Limit
From: SE 35th St

Updates Coming Soon

Site 7: Klahanie (Klahanie Blvd SE)

To: 245th Ave SE
From: Issaquah Pine Lake Road


No work in Klahanie until after the July 4th parade.  Please stay posted for updates.

Site 8: Carlton Heights, 204th Ave SE, 205th Ave SE

Crews will post door hangers and begin putting up 'No Parking' signs on June 21st.  'No Parking' signs cannot be enforced until June 25th.

Schedule:
Site Preparation will begin on June 22nd.

Grinding is anticipated to begin the week of June 25th.  This will include driveway edge grinding, planing and patching.

Unknown when paving will begin.



General Information about the Project:

Hours of work will be between 7:00 am and 5:00pm  daily. 

Driveway Access
 on most streets will remain open throughout most of the construction but traffic will be reduced to sharing a lane controlled by flaggers. In cul-de-sacs, crews will work with the residents to temporarily close the cul-de-sac so that paving operations can be completed quickly. During the actual paving process, there is typically a two to three hour time period where access to driveways is not allowed. This is time needed for the pavement to cool and harden before traffic can drive on it.

On Street Parking on the days of construction, on-street parking will need to be restricted. Signs will be posted in advance of the work to notify residents of the parking restrictions.

Waste and Recycling Schedule is not changed due to construction. When days of paving and waste collection coincide, we work with the collection service to adjust their route schedule and focus first on the streets that are being paved. If there is construction in your neighborhood, please be sure to have your waste and recycling out extra early.

Tree Trimming may need to be done in front of your house. If there is vegetation in front of your property that extends out into the street, it will need to be pruned back to allow the equipment to do the street resurfacing. Please trim the vegetation along your property if this is the case. City crews or the Contractor will trim vegetation as needed for the project. However, they will only be doing the minimum needed to clear the road for paving and some additional trimming may need to be completed afterwards by the adjacent property owner.

Street Cuts - Ordinance # 02001-78 prohibits the excavation of resurfaced or newly constructed roads for a minimum of five years following construction or paving. If you are planning to have any underground utility work done, such as water, sewer, telephone, gas, electrical, etc., you are strongly encouraged to expedite this work if it involves utility work under the new pavement. Please call us as soon as possible to coordinate this work.


The project has been advertised at Builders Exchange http://www.bxwa.com
The bid due date was 5/10/2018.
Council Award Date was 6/5/2018.

The work dates listed are subject to change due to weather, equipment and occasional scheduling conflicts with other regional paving work.

Updated: BR 06.21.18

Staff Contact