Past Updates


September 21, 2018

Road is Open

The mainline sewer is installed. The trench is being patched with pavement today and the roadway will be opened to traffic.  There is significant sewer work yet to be done, but the remainder of it can be completed while the roadway is open. We still recommend driving around the project during hours of work as travel delays due to construction activities will be ongoing and the roadway is quite rough due to all of the construction work.

Traffic Control -

Hours of construction work are Monday to Friday 7:00am to 5:00pm.  During these hours flaggers will be controlling traffic through the construction zone.  Depending on the construction work there will be times with significant travel delays. Please plan accordingly and consider using alternate routes during hours of construction.

September 7, 2018

Labor dispute resolved, work will begin again next week.

The labor union reached agreement with the construction companies yesterday and will be returning to work. The labor dispute was between the International Union of Operating Engineers 302 and the Associated General Contractors of Washington, the City was not involved with the dispute.

On Monday the crew will be on site getting equipment and plans ready to go for construction.  Work to finish the remaining 200 feet of sanitary sewer line could begin as early as Tuesday.  The mainline sewer is anticipated to be completed within two weeks of work restarting.Â

Traffic Control - Once crews are in action again, modifications will be made to the traffic control to keep school bus routes open.  The road will be closed for all other traffic between 225th Pl SE and 222nd Pl SE during hours of work.  There will be limited local access within the work zone during non-working hours. All other traffic should follow the detours around the construction zone, using either SE 20th St or Inglewood Hill Road for east-west travel.  The Sammamish Lower Commons Park can be accessed from the west using 218th Ave SE to get to SE 4th St. 


September 5, 2018

Construction on SE 4th St is still on hold for now.  A labor union strike for heavy equipment operators that began on August 21st has stopped construction for the sanitary sewer approximately 200 feet short of completion.  This labor dispute is between the International Union of Operating Engineers and the Associated General Contractors of Washington, the City is not part of the dispute. The work shutdown is impacting construction all over the region. The duration of the strike is unknown at this time. 

Modifications have been made to the traffic control so that local residents and school busses can get through the construction zone.  If you do not live on the street, please continue to use the detour routes.  If you have to use SE 4th St, please drive slow and cautiously. Thank you for your patience.  Construction will resume as soon as possible.

You can visit the parties webpages, links provided below, for more information pertaining to the labor dispute.

Associated General Contractors of Washington - https://www.agcwa.com/

International Union of Operating Engineers - http://iuoe302.org/


August 27, 2018

Construction on SE 4th St is on hold for now. A labor union strike for heavy equipment operators began last week and has stopped construction for the sanitary sewer approximately 200 feet short of completion. The duration of the strike is unknown at this time.

Road Closure Summary:

SE 4th St is closed between 225th Pl SE and 222nd Pl SE.  Access to Sammamish Lower Commons and 222nd Pl residents is from 218th Ave SE.


August 3, 2018

Construction for the sanitary sewer just passed the point of deepest excavation, almost 30 feet deep, and is getting close to the 222nd Pl SE intersection.  As crews work through the intersection, they will be placing maintenance aggregate for people to get access to their homes 222nd Pl and to the Lower Sammamish Commons.  Other work for the joint utility trench is moving quicker now that solutions have been developed to build near and around some older utilities that had not been documented on records.

Road Closure Summary:

For now, access to Sammamish Lower Commons and 222nd Pl residents is from 228th Ave SE.  Construction is anticipated to reach the 222nd Pl intersection by August 10th but timing could slide forward or back a few days depending on progress rate.  Work is anticipated to fill the intersection for up to four days. Once through the intersection, access will shift to the west side from 218th Ave SE. The traffic crew will be helping people impacted by the work to navigate the change.

July 27, 2018

Work is continuing on the sanitary sewer trench. The soil being excavated for the deep sanitary sewer is extremely hard due to the glacial compaction that occurred eons ago.  The crew is working hard but progress is slow as they fight through the dense soils, existing utilities and extreme summer heat. Trying to make up total project time, another crew is working on the joint utility trench.

Road Closure Summary:

Sewer construction is progressing from just East of 218th Pl towards 228th Ave SE. The closure between 218th Pl SE and 222nd Pl SE will extend into early August.  The construction crew will coordinate with residents in the road closure directly impacted by the construction work. Once sewer installation progress to 222nd Pl, the road closure will be shifted to between 222nd Pl SE and 225th Pl SE.  The Sammamish Commons Park will remain open during construction. The road closure is expected to last through August 18th.

July 13, 2018

SE 4th Street closed today to start construction on the sanitary sewer, a few days later than anticipated. The large excavator needed for sewer construction was delivered in pieces on three semis and took a few days extra to assemble. The photo above gives perspective on the size of the machine. Meanwhile, work continues on installation of the utility trench needed to underground the overhead wires along the corridor, though progress has slowed while the crew works around some older undocumented utility services lines that are interfering.

Road Closure Summary:

Sewer construction is progressing from just East of 218th Pl towards 228th Ave SE. Through July the road will be closed to thru traffic between the 218th Pl SE and 222nd Pl SE.  The construction crew will coordinate with residents in the road closure directly impacted by the construction work.  Once sewer installation progress to 222nd Pl, the road closure will be shifted to between 222nd Pl SE and 225th Pl SE.  The Sammamish Commons Park will remain open during construction.  The road closure is expected to last through August 18th.

July 6, 2018

Construction was light this week due to the July 4th Holiday.  Next week work will pick up again with the start of the sanitary sewer construction in addition to other utility construction work.  Large equipment is needed to complete the deep trench work and there will not be enough room for traffic to get around so portions of SE 4th St will be closed to thru traffic (local access will be allowed for residents within the closure area). Below is an exhibit showing alternate routes to get around SE 4th St.

Here is a summary of what to expect during the road closure:

Sewer construction will begin just East of 218th Pl and will move East. Through July the road will be closed to thru traffic between the 218th Pl SE and 222nd Pl SE.  The construction crew will coordinate residents in the road closure and directly impacted by the construction work.  Once sewer installation progress to 222nd Pl, the road closure will be shifted to between 222nd Pl SE and 225th Pl SE.  The Sammamish Commons Park will remain open during construction.  The road closure is expected to last through August 18th.

July 2, 2018

Construction for underground utilities has begun. Workers are currently installing conduits to underground the overhead utility wires. Installation of the deep sanitary sewer will begin the week following Fourth of July.  Large equipment is needed to complete the deep trench work and there will not be enough room for traffic to get around so portions of SE 4th St will be closed to thru traffic (local access will be allowed for residents within the closure area).  Below is an exhibit showing alternate routes to get around SE 4th St.


June 15, 2018

The SE 4th Street landscape is changing.  Crews are clearing the "footprint" of the new roadway.  It will look significantly different.  The old sixty feet of road right-of-way currently seems narrow since the only hard surface is the twenty feet of pavement and only had room for cars.  The new road right-of-way will be approximately seventy feet wide and will have space for people, bicycles, and cars.

The roadway clearing is expected to run most of July.  Utility Trench installation will be starting in the 218th Ave SE and SE 4th St intersection soon after the clearing work begins.  Flaggers will be directing traffic through a shared lane during this work.

Below are two conceptual images of what SE 4th St will look like once complete. The upper image represents the commercial area in the Town Center.  The other represents the westerly portion of the project which has an urban residential quality. (The photo above was taken June 1, 2018.)

June 1, 2018

The SE 4th Street landscape is about to change.  Next week crews will begin clearing the "footprint" of the new roadway.  It will look significantly different.  The old sixty feet of road right-of-way currently seems narrow since the only hard surface is the twenty feet of pavement.  The new road right-of-way will be approximately seventy feet wide and the hard surface - sidewalk and pavement -  will cover the majority of the space.  

The roadway clearing is expected to run most of July.  Utility Trench installation will be starting in the 218th Ave SE and SE 4th St intersection soon after the clearing work begins.  Flaggers will be directing traffic through a shared lane during this work.

Below are two conceptual images of what SE 4th St will look like once complete. The upper image represents the commercial area in the Town Center.  The other represents the westerly portion of the project which has an urban residential quality. (The photo above was taken June 1, 2018.)

Staff Contact