Ebright Creek Fish Passage Project

Project Updates

Week of 11/25: This week we held the project kick-off meeting. Over the month of December and into January the team will begin data collection and surveying. We will also be pursuing a grant with the Brian Abbott Fish Barrier Removal Board for construction funding.

Project Description

The Sammamish City Council adopted the 2017 to 2022 Six-Year Stormwater Capital Improvement Plan which identifies the Ebright Creek Fish Passage project design and construction in years 2020 and 2021. 

Timeline

Project Kick-off 11/25/2019
30% Design Spring 2020
60% Design Summer 2020
Final Design Winter 2021
Anticipated Construction Summer 2021

Vicinity Map.PNG

References

The project was awarded a grant through the Brian Abbott Fish Barrier Removal Board. View the project snapshot through the Recreation and Conservation Office.

The Ebright Creek Enhancement Plan was completed by David Evans and Associates, Inc. in 2012. It provides background information on hydraulic monitoring, stream alignment, and coordination for the project.

Additional files on kokanee salmon are available from King County at https://www.kingcounty.gov/services/environment/animals-and-plants/salmon-and-trout/kokanee/documents.aspx.

Ebright Creek monitoring information is available here.

This project will require coordination with King County on their culvert replacement for the East Lake Sammamish Regional Trail, South Sammamish Segment B. Information related to their project is available here.