UPDATE: Labor Dispute Ends; Work on SE 4th Street Project Resumes

Release Date: September 07, 2018

Following a two week strike by the International Operating Engineer’s Union, Local 302, work on the SE 4th Street Project will resume early next week. SE 4th Street remains closed to regular traffic for approximately two more weeks as crews finish up sanitary sewer installation and return the road to a safe, usable condition.

Other City construction projects affected by the strike, including overlay and turn pocket extension work along 228th Ave, are also set to resume. Due to the rain forecast next week, some work may be delayed to the following week.

Please visit out traffic alerts page for more information.