Timeline

Design - Construction

Consultant Selection September 2014 - December 2014 
Schematic Design  December 2014 - February 2015 
Design Development  February 2015 - April 2015 
Construction Plans  April 2015 - May 2015
Permit Review  May 2015 - June 2015 
Bidding  July 2015 - August 2015 
Phase I Construction   September 2015 - December 2015 
Anticipated Opening      January 2016