Timeline

Master Plan to Present

Master Plan July 2008 to July 2010
Phase I Design    Winter 2010 to Spring 2011
Phase I Construction Documents Spring 2011
Phase I Construction (except docks)   Summer/Fall 2011
Phase I Dock Construction    October 2012 to March 2013
Phase II Design, Permitting, Construction Documents January to July 2014
Phase II Partial Construction September 2014 to February 2015
ADA Access Improvements Design, Engineering, Construction Documents  September 2016 to March 2017
ADA Access Improvements Bid, Award April 2017 to May 2017
ADA Access Improvements Anticipated Construction  June 2017 to September 2017

timeline.JPG