Three week look-ahead 5/14 - 6/4/21

Below is your three week look-ahead from 5/14 - 6/4:

Update as of 5/28

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video(External link) with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 5/21

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video(External link) with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 5/14

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video(External link) with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Three week look-ahead 4/23 - 5/14/21

Below is your three week look-ahead from 4/23 - 5/14:

Update as of 5/14

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video(External link) with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 5/7

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Take a look at the ceremonial ribbon cutting video(External link) with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 4/30

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 p.m. on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 a.m. - 5:00 p.m., Saturday work hours: 9:00 a.m. - 6:00 p.m.

Update as of 4/23

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 PM on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM

Three week look-ahead 4/2-4/23/21

Below is your three week look-ahead from 4/2 - 4/23:

Update as of 4/23

The closure between 247th Place SE and Klahanie Dr. SE is open as of 2:30 PM on April 16, 2021. There are many people, businesses and organizations to thank and acknowledge. Stay tuned for a ceremonial ribbon cutting video with community acknowledgements. *Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • On Friday April 16th, the roadway opened up to the public between 247th PL SE and Klahanie. During work hours the public will still encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM

Update as of 4/16

The closure between 247th Place SE and Klahanie Dr. SE will open at 2:30 PM on April 16, 2021.

There are many people, businesses and organizations to thank and acknowledge. Stay tuned next week for a ceremonial ribbon cutting video with community acknowledgements.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • At 2:30 PM, Friday April 16th, the roadway will open up to the public between 247th PL SE and Klahanie. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Daytime project work hours are 7:30 AM - 5:00 PM, Saturday work hours: 9:00 AM - 6:00 PM

Update as of 4/9

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  • By end of shift Friday, April 9th, the contractor will have removed barrels from the roadway between 240th and 247th. The public will have full use of the roadway (both lanes in both directions) during off-hour times. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. The significant item of work to be completed after this week is sidewalk in front of the Issaquah Montessori; this is waiting for Utility Companies work to raise their vault lids.
  • By end of shift Friday April 16th, the roadway will open up to the public between 247th PL SE and Klahanie. During work hours the public will encounter short term (day time) lane closures as necessary to complete punchlist work. One of the significant items of work to occur after the opening of the roadway will be third party utilities taking a lane to finish installation of their vaults, lids, and make their necessary connections.
  • By May 1st, all punchlist work is schedule to be completed and traffic control will not be on the road until the contractor returns in June to begin the excavation for the stream mitigation work. We anticipate the third party utilities will be competed with this work by May 1, though this date is subject to change.

Update as of 4/2

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
  2. Remaining finish paving on the other side of project is planned for next dry weather.
  3. Utilities will be raising access lids in finished paved areas.
  4. Final bridge barrier section is nearly done.
  5. Guardrail and fence installation are underway.
  6. Topsoil and plants will be placed in roadway areas.
two rollers on fresh paving along four lanes of traffic with a median island and sidewalk on Issaquah Fall City Road

Three Week Look-Ahead 3/12 - 4/2/21

Below is your three week look-ahead from 3/12 - 4/2:

Update as of 4/2

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
  2. Remaining finish paving on the other side of project is planned for next dry weather.
  3. Utilities will be raising access lids in finished paved areas.
  4. Final bridge barrier section is nearly done.
  5. Guardrail and fence installation are underway.
  6. Topsoil and plants will be placed in roadway areas.

Update as of 3/26

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until April 16, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving has been completed over the project, and the west end between 240th and 247th has received finish paving and will be striped this Saturday.
  2. Remaining finish paving on the other side of project is planned for next dry weather.
  3. Utilities will be raising access lids in finished paved areas.
  4. Final bridge barrier section is nearly done.
  5. Guardrail and fence installation are underway.
  6. Topsoil and plants will be placed in roadway areas.

 

Update as of 3/16

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Base paving is expected to be completed by end of the week.
  2. Final overlay paving is scheduled to begin next week but forecasted rain will likely postpone that until dry weather.
  3. If we see dry days next week, pavers will be working 7 am – 5 pm, so please plan accordingly for traffic delays up to 30-minutes.
  4. Concrete work continues at private driveways, and remaining bridge barriers, sidewalks and curb and gutters.
  5. Mailbox preparation work is beginning for final locations.
  6. Utility work continues under the bridge and at a few other locations.

 

Update as of 3/12

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
  2. Expect delays up to 30-minutes during paving operations. Please plan accordingly.
  3. Duration – approximately 3 weeks.

Three week look-ahead 2/19 - 3/12/21

Below is your three week look-ahead for 2/19 - 3/12:

Update as of 3/12/21:

Issaquah-Fall City Road remains closed for construction between 247th PL SE and Klahanie DR SE. Local access will continue to be maintained between 240th and 247th during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Paving operations begin March 15 on the west end of the corridor between Eastridge Church and 247th PL SE (7 am – 5 pm).
  2. Expect delays up to 30-minutes during paving operations. Please plan accordingly.
  3. Duration – approximately 3 weeks.

Update as of 3/4/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Paving is scheduled to begin March 15, weather permitting.
  2. PSE Gas Crews will complete trench work near bridge by March 8, then continue with installation under the bridge while paving is underway.
  3. Bridge barrier placement continues.
  4. Remaining areas of sidewalk, curb and gutter continues.
  5. Roundabout stamped concrete truck aprons are poured.
  6. Fencing will begin this week.
  7. Landscaping – topsoil placement ongoing and planting to begin soon.

Update as of 2/25/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Bridge traffic barrier pour – first section has cured, and forms have been stripped. Work continues on remaining sections.
  2. Moment slabs supporting traffic barriers at the bridge approaches are completed. Sidewalks are now being formed atop these.
  3. Sidewalk grading underway in remaining areas.
  4. PSE Gas crews continue to install gas main under the bridge.
  5. Roundabouts – prepping for curb installation and truck aprons.
  6. Landscaping – installing topsoil behind sidewalks
  7. Fence installation beginning soon.

Update as of 2/18/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Bridge barrier pour scheduled this week on south side of bridge.
  2. Moment slab rebar is being installed now at bridge approach, and the last segment will soon be poured.
  3. PSE Gas continues to install utilities under the bridge.
  4. Curb installation at splitter island and median islands underway.
  5. Roundabout truck aprons at 242nd and SE Klahanie Drive are being constructed.
  6. Roundabout landscape preparation is underway.

Three Week Look-Ahead 1/29 - 2/19/21

Below is your three week look-ahead for 1/29 - 2/19:

Update as of 2/18/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

*Safety Reminder – Please observe the contractor’s “Sidewalk Closed” and “No Trespassing” signs at all times.

  1. Bridge barrier pour scheduled this week on south side of bridge.
  2. Moment slab rebar is being installed now at bridge approach, and the last segment will soon be poured.
  3. PSE Gas continues to install utilities under the bridge.
  4. Curb installation at splitter island and median islands underway.
  5. Roundabout truck aprons at 242nd and SE Klahanie Drive are being constructed.
  6. Roundabout landscape preparation is underway.

Update as of 2/11/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

  1. PSE Gas main installation under bridge continues for approximately 2 more weeks.
  2. Storm sewer and water main installation under bridge continues.
  3. Sidewalk construction on north side of bridge is completed.
  4. Barrier on the south side of bridge is being formed.
  5. Concrete work continues over next 2 weeks for medians, stamped concrete, and remaining sidewalks, followed by road grade preparation for paving.
  6. Trenching continues to bring power to streetlights.

Updates as of 2/5/2021:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will remain until May 1, 2021.

  1. Utility installation under bridge – dry utilities have been completed, with water main and storm sewer installation now underway.
  2. Bridge barrier concrete pour scheduled for next week.
  3. PSE Gas utility relocation (by third party) continues within the bridge approaches.
  4. New pedestrian crossing signal (HAWKS) at the Pacific Cascade Middle School entrance is now activated, and streetlights are being wired for power.
  5. Base paving done at intersections of 242nd, 247th and Klahanie Drive SE, opening roundabouts for circulation.
  6. The large new detention pond at Klahanie Drive SE has been completed and is now collecting stormwater.
  7. Curbs and gutters for roundabouts and median islands will be installed over next 2 weeks.

Update as of 1/29:

Due to unforeseen circumstances, including construction delays caused by necessary third party utility relocations and inclement weather, the City of Sammamish Public Works Department has determined the road opening by end of January is not feasible.

The City of Sammamish has looked at options to hasten the construction or partial openings, but has determined in an abundance of caution that these options are not safe nor realistic due to weather events and fiscal constraints.

Upon reviewing the contractor's updated and current schedule, and the status of utility relocations, the bridge and roadway are now scheduled to be opened to traffic on May 1, 2021.

We understand and apologize for this inconvenience and thank you for your continued patience as we work to improve the City’s traffic flow.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Important Issaquah-Fall City Road Construction Update on Road Closure

28 Jan 2021

UPDATED:

Issaquah Fall City Road Closure Delay – Follow up to Community Comments

The City of Sammamish wishes to thank residents for submitting your questions and comments on the Issaquah Fall City Road closure delay.

We acknowledge your concerns about the project delay. We also acknowledge that the timing of our announcement caught residents by surprise.

We commit to doing better. Part of this entails providing more transparency to the public on the primary reasons for the delays. The City's Communications team is compiling all your questions and comments. Our Public Works team will work on responses that will be conveyed to the public via the City’s communication platforms by next Friday afternoon, February 5.

Original Message

Issaquah Fall City Road Update:

Due to unforeseen circumstances, including construction delays caused by necessary third party utility relocations and inclement weather, the City of Sammamish Public Works Department has determined the road opening by end of January is not feasible.

The City of Sammamish has looked at options to hasten the construction or partial openings, but has determined in an abundance of caution that these options are not safe nor realistic due to weather events and fiscal constraints.

Upon reviewing the contractor's updated and current schedule, and the status of utility relocations, the bridge and roadway are now scheduled to be opened to traffic on May 1, 2021.

We understand and apologize for this inconvenience and thank you for your continued patience as we work to improve the City’s traffic flow.

Three Week Look-Ahead 1/8 - 1/29/21

Below is your three week look-ahead for 1/8 - 1/29:

Update as of 1/29:

Due to unforeseen circumstances, including construction delays caused by necessary third party utility relocations and inclement weather, the City of Sammamish Public Works Department has determined the road opening by end of January is not feasible.

The City of Sammamish has looked at options to hasten the construction or partial openings, but has determined in an abundance of caution that these options are not safe nor realistic due to weather events and fiscal constraints.

Upon reviewing the contractor's updated and current schedule, and the status of utility relocations, the bridge and roadway are now scheduled to be opened to traffic on May 1, 2021.

We understand and apologize for this inconvenience and thank you for your continued patience as we work to improve the City’s traffic flow.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 1/22:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.
  7. Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

 

Update as of 1/15:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.
  7. Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

 

Update as of 1/8:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Three Week Look-Ahead 12/18/20 - 1/8/21

Below is your three week look-ahead for 12/18 - 1/8:

Update as of 1/8:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 12/25:

Issaquah-Fall City Road (IFCR)

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

 

Update as of 12/18:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume in early December, as the utilities complete the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Three Week Look-ahead 11/27 - 12/18/20

Below is your three week look-ahead for 11/27 - 12/18:

Update as of 12/18:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume in early December, as the utilities complete the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

 

Update as of 12/4:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. Construction of the 242nd roundabout will resume in early December, as the utilities complete the final relocations in this area.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

 

Update as of 11/27:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Bridge crews will work a bit later than usual on December 2nd (weather permitting) to place concrete on deck two. Instead of finishing by 5 PM, the crews expect to finish between 6 PM and 8 PM.
  2. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  3. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  4. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  5. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  6. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  7. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Three Week Look-Ahead 11/6 - 11/27/20

Below is your three week look-ahead for 11/6 - 11/27

Update as of 11/27:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE will now remain until the end of January 2021.

  1. Bridge crews will work a bit later than usual on December 2nd (weather permitting) to place concrete on deck two. Instead of finishing by 5 PM, the crews expect to finish between 6 PM and 8 PM.
  2. Construction of the bridge is underway with plans to open two lanes of traffic on the north half of the bridge by the end of January 2021. The south half of the bridge will remain closed while utilities are incorporated in the bridge abutment retaining walls (small wall connections).
  3. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  4. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  5. Construction of the 242nd roundabout will resume earlier December, as the utilities completing the final relocations in this area.
  6. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  7. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 11/20:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 11/13:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 11/6:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Three Week Look-Ahead 10/16 - 11/6/20

Below is your three week look-ahead for 10/16 - 11/6

Update as of 11/6:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Update as of 10/30:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 10/23:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  5. The contractor will be working on the new detention pond and storm drainage facilities at the northwest corner of the intersection of Issaquah Fall City Road and Klahanie Drive SE.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 10/16:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. The contractor is also installing a new water main between 242nd and 247th in conjunction with this project.
  5. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Three Week Look-Ahead 9/25 - 10/16/20

Below is your three week look-ahead for 9/25 - 10/16

Update as of 10/16:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete sidewalk along the north side and placing concrete in the median islands.
  4. The contractor is also installing a new water main between 242nd and 247th in conjunction with this project.
  5. PSE is expected to lower their gas main at the intersection of 242nd in the early part of November, once completed the remaining utilities can be lowered and the contractor can resume construction of the roundabout.
  6. With the daylight hours shortening in the fall and winter, the contractor is expected to work on the occasional Saturdays to take advantage of daylight hours, weather and keep on schedule.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m., Saturday Work Hours 9:00 a.m. – 6 p.m.

Update as of 10/9:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and placing concrete in the median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school and 242nd Ave SE. The work is weather dependent; sunny days next week should allow the asphalt pavement to be done. There will be more construction traffic through the site as a result.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m.

Update as of 10/2:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and placing concrete in the median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school and 242nd Ave SE. The work is weather dependent; sunny days next week should allow the asphalt pavement to be done. There will be more construction traffic through the site as a result.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7:30 a.m. to 5 p.m.

Update as of 9/25

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school and 242nd Ave SE. During the week of September 28, the contractor will be finishing the current phase of placing asphalt along the north half of the site and at the intersection of 242nd, 247th, and Klahanie Drive and Issaquah Fall City Road, as well as the intersection of SE 46th. The work is weather dependent; sunny days next week should allow the asphalt pavement to be done. There will be more construction traffic through the site as a result.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

Three Week Look-Ahead 9/4 - 9/25/20

Below is your three week look-ahead from 9/4 - 9/25

Update as of 9/25:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway. Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school and 242nd Ave SE. During the week of September 28, the contractor will be finishing the current phase of placing asphalt along the north half of the site and at the intersection of 242nd, 247th, and Klahanie Drive and Issaquah Fall City Road, as well as the intersection of SE 46th. The work is weather dependent; sunny days next week should allow the asphalt pavement to be done. There will be more construction traffic through the site as a result.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

Update as of 9/18

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams (Small wall connections).
  2. Construction of the retaining walls and bridge approaches on the east and west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school. During the week of September 21, the contractor will be placing asphalt along the north half of the site and at the intersection of 242nd, 247th and Klahanie Drive and Issaquah Fall City Road, as well as the intersection of 247th and SE 46th. There will be more construction traffic through the site as a result.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Update as of 9/11

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. Construction of the bridge is underway and on schedule to complete in December. The contractor is continuing to work on the bridge understructure by installing the concrete diaphragms between the beams. (Small wall connections)
  2. Construction of the retaining walls and bridge approach from 247th on the west side of the bridge is currently being built.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor is installing the concrete curb and sidewalk along the north side and median islands. The contractor will also continue to work at the intersection of 247th Ave. SE near the middle school. Asphalt for the roadway and roundabout at 247th is scheduled to occur at the end of September.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Update as of 9/4:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor completing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb, and sidewalk placement have been extended due to work related to the underground utilities. The contractor will continue to work at the intersection of 247th Ave. SE near the middle school. Placement of asphalt is occured at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

Three Week Look-Ahead 8/14 - 9/4/20

Below is your three week look-ahead for 8/14 - 9/4

Update as of 9/4:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor completing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb, and sidewalk placement have been extended due to work related to the underground utilities. The contractor will continue to work at the intersection of 247th Ave. SE near the middle school. Placement of asphalt is occured at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

Update as of 8/28:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor completing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor will continue to place girders on the nights of Monday August 31st, and Tuesday September 1st.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb, and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week at the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

NOTICE OF NIGHTTIME WORK: Hours are 7 p.m. to 7 a.m. during the nights of August 31 and September 1. Work includes bridge girder delivery and installation. Equipment will consist of two large cranes and semi-truck transports.

Update as of 8/21:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor completing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor will be placing girders during the nights of August 24th through August 27th, and the nights of Monday August 31st, and Tuesday September 1st.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb, and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week at the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Daytime Project work hours are 7 a.m. to 5 p.m.

NOTICE OF NIGHTTIME WORK: Hours are 7 p.m. to 7 a.m. during the nights of August 24, 25, 26, 27, 31, and September 1. Work includes bridge girder delivery and installation. Equipment will consist of two large cranes and semi-truck transports.

 

Update as of 8/14:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor performing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor is working to complete the top beams to the substructure in preparation of the girder installation. The girders for the bridge are being delivered and installed during the week of August 24th. Girder installation will be occurring during the night time hours of August 24-August 28.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Night Time Bridge Construction 8/24-27, 8/31 and 9/1/20

The contractor constructing the bridge along Issaquah Fall City Road will be installing bridge girders during the night time hours of 7:00 PM to 7:00 AM on August 24th-27th, 31st, and 9/1

When: Girders are scheduled to be delivered beginning on the night of Monday August 24th. The work will run though Thursday August 27th, stop over the weekend and finish during the nights of Monday August 31st and Tuesday September 1st.

Hours: 7:00 PM - 7:00 AM

Girder Delivery Route: Johansen Construction Company, Inc. and its subcontractors will be delivering bridge girders through SE Issaquah-Fall City Road with the limits being WA-202 (Redmond-Fall City Road) to Klahanie Drive SE.

Night Time Work Noise: The contractor has been restricted to limit the noise down to a lower level. Equipment will be directed through radio and hand signals. Back up beeps on the vehicles will not be in operation during night hours.

Site Access: The portion of the roadway where the bridge construction is will remain closed to the public. Access for the girders will be through the Klahanie Drive intersection along Issaquah Fall City Road. Please work with the flaggers for travel through the site during delivery and observe all construction signs. We apologize for any inconvenience while we make these deliveries.

Thank you very much in advance for your patience and cooperation with construction of this large capital project for the City.

Questions or Comments?

City Contact: Andrew Zagars P.E.

azagars@sammamish.us

(425) 295-0561

sunset at the bridge construction site as girders are being placed

Three Week Look-Ahead 7/24 - 8/14/20

Below is your three week look-ahead for 7/24 - 8/14

Update as of 8/14:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. There will be a contractor performing work on the sidewalks and wheelchair ramps during the week.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor is working to complete the top beams to the substructure in preparation of the girder installation. The girders for the bridge are being delivered and installed during the week of August 24th. Girder installation will be occurring during the night time hours of August 24-August 28.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 8/7:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  1. The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection are currently on schedule to start the second week of August.
  2. Construction of the bridge is underway and on schedule to complete in December. The contractor has completed the columns for each of the bridge sections and are working on the top cross beams. The girders for the bridge are expected to be delivered and installed at the end of August.
  3. Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work, concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of August.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/31

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is still on schedule to last through the end of December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection are currently on schedule to start the second week of August.
  • Construction of the bridge is underway and on schedule to complete in December. The contractor has completed the columns for each of the bridge sections and are working on the top cross beams. The girders for the bridge are expected to be delivered and installed at the end of August.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement have extended into August due to work related to the underground utilities. The contractor will continue to work next week in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is currently on schedule to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/24:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection will be made at the end of July/early August. The new street lights are expected to be installed and operational by the end of July.
  • Construction of the bridge in underway. The contractor has completed the columns for each of the bridge sections. The contractor is currently working on the pile caps and the access road for the girder delivery. The girders are expected to begin delivery in 2 weeks.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement will continue through July. The contractor will continue to work in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is expected to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Three Week Look-Ahead 7/3 - 7/24/20

Below is your three week look-ahead for 7/3 - 7/24

Update as of 7/24:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection will be made at the end of July/early August. The new street lights are expected to be installed and operational by the end of July.
  • Construction of the bridge in underway. The contractor has completed the columns for each of the bridge sections. The contractor is currently working on the pile caps and the access road for the girder delivery. The girders are expected to begin delivery in 2 weeks.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement will continue through July. The contractor will continue to work in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is expected to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/17:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk, final curb adjustment, and curb ramps around the intersection will be made at the end of July/early August. The new street lights are expected to be installed and operational by the end of July.
  • Construction of the bridge in underway. The contractor has completed the columns for each of the bridge sections. The contractor is currently working on the pile caps and the access road for the girder delivery. The girders are expected to begin delivery in 2 weeks.
  • Between 242nd and 247th Ave. SE, traffic remains on the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement will continue through July. The contractor will continue to work in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is expected to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times. Please remember to obey all the stop signs and speed limits in the area.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/10:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced this month. The work will include relocating existing ramps and placement of new concrete and curb in around the roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge in underway. The contractor has completed the columns for each of the bridge sections. Next, the contractor will begin work on the top concrete caps that connect each of the columns. Once those are complete, the bridge girders will be delivered to the site for installation. The girders are expected to begin delivery in 2 weeks.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Grading work and concrete curb and sidewalk placement will continue through July. The contractor will continue to work in the intersection of 247th Ave. SE near the middle school. Placement of asphalt is expected to occur at the end of July.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Project work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th continue to begin at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th continue to start at 7:30 a.m., following the required health check-up.

Update as of 7/3:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced in July. The work will include relocating existing ramps and placement of new concrete and curb in around the Roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Also concrete curb and sidewalk placement is expected to begin.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Three-week look ahead 6/12 - 7/3/20

Below is your three week look-ahead for 6/12 - 7/3

Update as of 7/3:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced in July. The work will include relocating existing ramps and placement of new concrete and curb in around the Roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Also concrete curb and sidewalk placement is expected to begin.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 6/19:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive. The sidewalk around the intersection will be replaced in July. The work will include relocating existing ramps and placement of new concrete and curb in around the Roundabout to better improve access for pedestrians to the crossing locations.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area. The contractor and the utility companies will be working on relocations in these limits. Also concrete curb and sidewalk placement is expected to begin.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 6/12:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Three Week Look-Ahead 5/29 - 6/12/20

Below is your three week look-ahead for 5/29 - 6/12

Update as of 6/5/20

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far all of the underground shafts have been completed. The contractor is currently verifying the installation of the drilled shafts and will start constructing upward out of the ground. The area is closed to the public.
  • Between 242nd and 247th Ave. SE, traffic has been shifted to the south side of the roadway.Work continues along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 7 a.m. to 5 p.m.

Bridge crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 5/29/20

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.
  • Starting next week, the bridge work will be coming out of the ground and starting to move up.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Updated: Work hours are 7 a.m. to 5 p.m.

Bridge-drilling crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Three Week Look-Ahead 5/8 - 5/29/20

Below is your three week look-ahead for 5/8 - 5/29

Update as of 5/22/20

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Updated: Work hours are 7 a.m. to 5 p.m.

Bridge-drilling crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Update as of 5/8/20:

Issaquah-Fall City Road remains closed for construction. Local access will be maintained during the closure. The closure between 247th Place SE and Klahanie Dr. SE is expected to last through December 2020.

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled once all the parts arrive.
  • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Updated: Work hours are 7 a.m. to 5 p.m.

Bridge-drilling crews between Klahanie Dr. SE and 247th have started at 7:00 a.m., following the required health check-up. Road crews between 242nd and 247th have started at 7:30 a.m., following the required health check-up.

Three Week Look-Ahead 4/17/20 - 5/8/20

Below is your three week look-ahead for 4/17 - 5/8

Update as of 4/29/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
  • Construction of the bridge has begun. So far, 6 of the 12 drilled underground shafts have been completed. Six more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic has been shifted to the south side of the roadway.Work has started along the north half of the roadway in this area.
  • The contractor will continue to work in the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Road to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 8 a.m. to 5 p.m.

CLOSURE NOTICE: Issaquah Fall City Road is closed for construction.

  • Local access will be maintained during the closure.
  • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.

 

Update as of 4/24/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Only final touch-ups are remaining, which are being scheduled.
  • Construction of the bridge has begun. So far, two of the drilled underground shafts have been completed. Ten more remain, then they will start building the above-ground work. The area is closed to the public.
  • Paving between 242nd and 247th Ave. SE is complete. Traffic is expected to be shifted to the south side of the roadway within the next two weeks.
  • The contractor will continue to work along the south side of the intersection of 247th Ave. SE near the middle school.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 4/17/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Remaining work is expected to be completed on Monday, April 20th.
  • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
  • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving started on Friday, April 17 and is scheduled to be completed during the week of April 20th.
  • Starting Monday, April 20th, the bridge between 247th Ave SE and Klahanie Dr SE will begin. The drillers will be mobilizing on site and start drilling the concrete bridge columns. The area will be fenced off from the public.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 8 a.m. to 5 p.m.

CLOSURE NOTICE:

Issaquah Fall City Road closed for construction.

  • Local access will be maintained during the closure.
  • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.

Three Week Look-Ahead 3/27/20-4/17/20

Below is your three week look-ahead for 3/27-4/17

Update as of 4/17/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. Remaining work is expected to be completed on Monday, April 20th.
  • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
  • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving started on Friday, April 17 and is scheduled to be completed during the week of April 20th.
  • Starting Monday, April 20th, the bridge between 247th Ave SE and Klahanie Dr SE will begin. The drillers will be mobilizing on site and start drilling the concrete bridge columns. The area will be fenced off from the public.

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Work hours are 8 a.m. to 5 p.m.

CLOSURE NOTICE:

Issaquah Fall City Road closed for construction.

  • Local access will be maintained during the closure.
  • Beginning April 18th, the roadway closure will remain between 247th Place SE and Klahanie Dr. SE. This closure is expected to last through December 2020.

Update as of 4/10/20:

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Blvd.
  • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving is anticipated to occur during the week of April 13th, after which the traffic will be shifted to the south half.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 4/3/20:

  • The contractor will be working on the Samm Plat waterline between 242nd Ave. SE and 247th Ave. SE. There will be a one-lane closure and a uniformed police officer at the 247th intersection this Monday, Tuesday, and Thursday.
  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link are completing their removal and relocation of their services between 247th Ave SE and Klahanie Dr SE.
  • Final preparation for paving along the south half of the roadway between 242nd and 247th Ave. SE continues. Paving is anticipated to occur during the week of April 13th, after which the traffic will be shifted to the south half.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 4/2/20:

Starting on Monday, April 13th, 2020, Issaquah Fall City Road will be closed for construction.

  • During the week of April 13th through April 18, the road will be closed between 245th Lane SE and Klahanie Dr SE for roadway grading and shifting of the roadway access in front of Pacific Cascade Middle School.
  • Local access will be maintained during the closure.
  • The section between 245th Lane SE and 247th Place SE will reopen by the end of the day on April 18th, weather permitting.
  • Starting on Monday, April 20th, the roadway closure will be between 247th Place SE and Klahanie Blvd. This closure is expected to last through December 2020.

Three Week Look-Ahead 3/6/20-3/27/20

Below is your three week look-ahead for 3/6/20-3/27/20

Update as of 3/27/20

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th and 247th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

DATES

Estimated dates for the ROAD CLOSURE are April 13, 2020, to December 31, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.

 

Update as of 3/13/20

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th and 247th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times.

Update as of 3/6/20

  • Puget Sound Energy (PSE) will be working this Saturday, 3/7, from 9 a.m. to 6 p.m. along the south side of Issaquah-Fall City Road between 247th and Klahanie Blvd. They will be trimming trees to help set new power poles.
  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
    • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road,may result in shorter drive times.

DATES

  • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
  • August 2021 - END CONSTRUCTION

Three Week Look-Ahead 2/18/20-3/10/20

Below is your three week look-ahead for 2/18-3/10

Update as of 3/6/20

  • Puget Sound Energy (PSE) will be working this Saturday, 3/7, from 9 a.m. to 6 p.m. along the south side of Issaquah-Fall City Road between 247th and Klahanie Blvd. They will be trimming trees to help set new power poles.
  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
    • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road,may result in shorter drive times.

DATES

  • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
  • August 2021 - END CONSTRUCTION

Update as of 2/28/20

  • The temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St/E Beaver Lake Dr. SE is operational. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed.
  • When the concrete work is complete, work will begin on the new traffic circle at 247th and SE 45th Way.
  • Puget Sound Energy (PSE) Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench between 245th and 247th.
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines between 247th and Klahanie to allow the bridge construction to begin.
    • PSE Electric (Asplundh) will be removing trees in the new PSE utility corridor on the south side of the road on private property in King County.
    • The contractor will be removing trees on the north side of the road that have been identified for removal by the project arborist. Note: All trees in direct conflict with the structure are assessed for health and chances for survival by the project arborist. All healthy, viable trees are saved and/or moved.
  • The new concrete student walkway and stairs leading up to the front entrance of Pacific Cascade Middle School are being built.
  • Drainage installation continues at and around 245th.
  • Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road,may result in shorter drive times.

DATES

  • Estimated dates for the ROAD CLOSURE are March 28th, 2020, to November 28th, 2020, between 247th and Klahanie Blvd. only. Updates on the actual closure date will be posted ASAP.
  • August 2021 - END CONSTRUCTION

Update as of 2/21/20

The layout for the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St./& E Beaver Lake Dr. SE has been completed. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed in the near future.

Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS):

  • Through 3/27/20, PSE Electric, Comcast, Century Link, & Verizon are relocating to a joint utility trench
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines to allow the bridge construction to begin
  • Storm drainage installation continues
  • Construction continues on the new student walkway leading up to the front entrance of PCMS
  • A buried roadway section in the southern shoulder of Issaquah-Fall City Road will be dug up and removed

Please note that during peak delays, using the project detour route, Issaquah-Beaver Lake Road to Issaquah-Pine Lake Road, may result in shorter drive times.

Update as of 2/20/20

Next Monday (2/24/20), single lane closures along Issaquah-Fall City Road will continue to occur for the installation of utilities.

Update as of 2/18:

The layout for the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave. SE/SE 32nd St./& E Beaver Lake Dr. SE has been completed. The roundabout will remain open while curb, truck apron, paint lines, lighting, & pedestrian crossing work is completed in the near future.

Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS):

  • Through 3/27/20, PSE Electric, Comcast, Century Link, & Verizon are relocating to a joint utility trench
  • PSE Electric, Comcast, & Century Link will relocate existing poles and lines to allow the bridge construction to begin
  • Storm drainage installation continues
  • Construction continues on the new student walkway leading up to the front entrance of PCMS
  • A buried roadway section in the southern shoulder of Issaquah-Fall City Road will be dug up and removed

Please note that during peak delays, using the project detour route, Issaquah-Beaver Lake Road to Issaquah-Pine Lake Road, may result in shorter drive times.

Three Week Look-Ahead 2/11/20-3/3/20

Update as of 2/18/20:

Traffic Alert! On Thursday (2/20/20) between the hours of 9am-3pm, traffic will be restricted at the temporary roundabout intersection of Issaquah Beaver Lake Road and 256th Ave/West Beaver Lake Drive with flaggers. The contractor will be restricting the roundabout to only one leg access at a time. There will be flaggers at each of the four approaching legs to the intersection to help guide traffic through and around the location of construction. Next Monday, (2/24/20) single lane closures along Issaquah Fall City Road will continue to occur for the installation of utilities.

Update as of 2/13/20:

NEW Issaquah-Fall City Road Closure FAQs, with answers from our stormwater experts to the questions, "The road is still flooded. Why isn’t the water going down faster?", "What is the City doing to fix this? Can you pump the water somewhere?", "How long will the road remain flooded/closed?", and "How often are we going to see flooding events like this?"

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 2/11/20:

2/11/20

The Contractor for the Issaquah-Fall City Road project is taking advantage of the break in the weather to construct the roundabout at the intersection of Issaquah Beaver Lake Road and 256th Ave SE beginning today, Tuesday, February 11.

The work has been planned and signed for a while, but the weather has delayed work up to this point. The contractor will be placing the paint striping and signage, and using orange barrels and cones until the final concrete curbs are installed over the existing asphalt roadway. The concrete work can occur with light rains and is planned to be completed by this weekend.

The contractor will be working in the roadway between the hours of 9:30 am and 3:00 pm to account for school traffic at the neighboring middle school. Please expect flaggers during the hours of construction. Until the roundabout is complete, please follow the posted stop signs that have been used while the flooding of Issaquah-Fall City Road has occurred.

We know there's been a lot of change at this intersection over the last week, and we thank you for using care and patience as you drive. Challenger Elementary and Beaver Lake Middle are walking schools, so please be mindful of children in the area. This roundabout will be a change for them too, so please be aware that the children might not be as aware of their surroundings as they usually are.

If you have any questions please, contact the project manager, Sam Park, at 425-295-0538.

Issaquah-Fall City Road (IFCR) 2/7/20

Please note that during peak delays, using the project detour route, Issaquah Beaver Lake Rd to Issaquah Pine Lake Road, may result in shorter drive times

Work is currently occurring primarily in front of Pacific Cascade Middle School (PCMS), on the south side of the roadway:

  • PSE Gas is increasing the depth of their high pressure gas line located beneath IFCR
  • PSE Electric, Comcast, Century Link, & Verizon are relocating to a Joint Utility Trench
  • Utilities are finalizing plans to relocate existing poles and lines to allow the bridge construction to begin
  • Storm drainage installation is continuing on the project
  • Construction continues on the new student walkway and wall leading up to the front entrance of PCMS
  • Bridge Column Rebar Cages are being built by steel fabricators and detailers off-site
  • Construction on the temporary roundabout at SE Issaquah-Beaver Lake Rd./256th Ave SE/E Beaver Lake Dr. is expected to begin on Tuesday, Feb. 11.

Three Week Look-Ahead 1/22/20-2/12/20

Update as of 2/6/20:

Heads up for later this week: Issaquah-Fall City Road, in the area in front of Pacific Cascade Middle School, will have one lane closed from Wednesday, February 5, through Monday, February 10, so that the general contractor can install storm drainage pipe.

Traffic will be down to a single lane with flaggers between the work hours of 9:30 a.m. to 3:30 p.m.

Though there is a chance that the contractor will complete this work by Friday, please be prepared for the work to go through Monday the 10th.

 
Update as of 1/23/20:
  • During peak delays, using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times
  • Current items of work:
    • The initial roadway lowering has been completed on the south side of the road in front of PCMS
    • PSE Gas, PSE Electric, Comcast, Century Link, & Verizon are relocating utilities in this lowered section of the road
    • Storm drainage installation is continuing
    • Construction of the pedestrian path and the retaining wall leading to the front entrance of PCMS
    • The temporary roundabout at SE Issaquah-Beaver Lake Rd/256th Ave SE/E Beaver Lk Dr is pending, and is dry weather dependent for striping

On Wednesday, January 21, a PSE subcontractor will allowed to begin work at 9:00 am, rather than at the regular start time of 9:30 am. This is to allow time for the connection of an upsized 6-inch gas line for Puget Sound Energy. This is the third, and final, tie-in required on the project.

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 1/22/19:
  • Please be prepared for additional delays as utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link).
  • Using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times during peak delays.
  • Project work is primarily in front of Pacific Cascade Middle School (PCMS)
  • Storm drainage installation has begun in the center of the roadway
  • By January 23, the south side of the road will be lowered by 5 feet to remove the existing "hump"
  • Utilities will be installing a PSE gas line and a joint utility trench once the road is lowered
  • Work continues on the new pedestrian path and retaining wall leading to the PCMS front entrance
  • The temporary roundabout at SE Issaquah Beaver Lake Rd./256th Ave./East Beaver Lake Dr. is pending, dependent on dry weather for striping

Three Week Look-Ahead 1/10/20-1/31/20

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 1/10/19:

  • Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
  • During peak delays, using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times.
  • Project work is occurring primarily in front of Pacific Cascade Middle School (PCMS)
  • Storm drainage installation has begun in the center of the roadway.
  • By January 20th, the south side of the road will be lowered by 5-feet to remove the existing "hump"
  • Work continues on the new pedestrian path and retaining wall that leads up to the front entrance of PCMS

Three Week Look-Ahead 12/20/19

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 12/20/19:

  • UPDATE: Please be prepared for additional delays as Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
    • During peak delays, using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times
  • The two KLAHANIE development signs will be demo'd soon. Replacement signs will be designed and installed by the Klahanie Homeowners Assoc
  • The Pacific Cascade Middle School (PCMS) sign will be removed. A replacement design and location will be coordinated directly with PCMS and ISD
  • Grading and drainage structure installation are some of the next items of work for the project

Three Week Look-Ahead 12/3/19

Revised 12/4/19*

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 12/3/19:

  • UPDATE: Please be prepared for additional delays as vital Utility relocations are currently impacting traffic (PSE Gas, PSE Electric, Comcast, Century Link)
  • Using the project detour route, Issaquah Beaver Lake Rd-Issaquah Pine Lake Road, may result in shorter drive times
  • Construct Stormwater facilities
  • Clear project vegetation in right of way
  • Prep for construction of a Temporary Roundabout at 256th (E Beaver Lake Dr) & SE Issaquah-Beaver Lake Road
  • Please note: The Pacific Cascade Middle School (PCMS) Sign will be removed soon. A replacement design and location is being coordinated directly with PCMS and ISD. Thank you!

Three Week Look-Ahead 11/5/19

Below is your three week look-ahead for Issaquah Fall City Road Phase 1 for 11/5/19:

  • Install Stormwater pipes near the Eastridge church entrance
  • Relocate Utilities (PSE Gas, PSE Electric, Comcast, Century Link, Williams)
  • Prepare the hill in front of the school for a pedestrian walkway, stairs, and block wall
  • Clear project vegetation in right of way
  • Preparation at 256th (E Beaver Lake Dr) & SE Issaquah-Beaver Lake Road for the construction of the Temporary Roundabout
  • Please note: The Pacific Cascade Middle School (PCMS) Sign will be removed soon. A replacement design and location is being coordinated directly with PCMS and ISD. Thank you!