Carrier Subdivision

INTRODUCTION

The Carrier Subdivision (see vicinity map below for reference), started construction in September 2019. The project site is more than 14 acres in size, of which about 8.7 acres is preserved as critical area (wetland, streams, and habitat), tree retention, recreation, and open space.

Vicinity Map

Timeline

January 29, 2016 – Preliminary Subdivision application submitted.

February 2, 2016 – Preliminary Subdivision application vested.

July 30, 2018 – Preliminary subdivision approved for 35 lots (see site plan below).

August 15, 2019 – Site Development Permit issued; this permit requires certain trees to be retained, allows certain trees to be removed, and allows part of the site to be graded.

September 2019 – Construction began.

September 16, 2019 – Erosion control measures (such as a silt fence and rock-bed construction entrance for heavy machinery) installed.

October to November 2019 – Stormwater vault construction to begin.

October 2019 to January 2020 – Right-Of-Way (ROW) improvements along SE 8th Street to begin.

December 2019 to March 2020 – ROW improvements along 214th Avenue NE to begin.

Site Plan

CONTACTS

Community Development: Avril Baty, Principal Planner – abaty@sammamish.us

Please contact Avril if you have questions about the critical areas, trees, and mitigation measures. Avril also accepts requests for additional information to be posted to the website. 

Public Works: Tom Tubbs, Construction Inspector – ttubbs@sammamish.us

Please contact Tom if you have questions about the project's grading, erosion control measures, and right-of-way improvements. Additionally, Tom is the contact if there is run-off from the site that contains silt and/or dirt. 

Developer: Jeff Peterson, Toll Brothers – jpeterson@tollbrothers.com

Please contact Jeff Peterson if you have questions about the construction timeline.