212th Ave SE Non-Motorized Improvements: SE 24th St to Crossings at Pine Lake

Subscribe to project updates.

 

Summary

Design is under way for sidewalk and landscape planter strip on the west side of 212th Ave SE between SE 24th and the Crossings at Pine Lake subdivision. Also, both sides of the street will receive widened shoulders to accommodate bicycles.

Project Updates   

Design is 95% complete, and is now awaiting permits.

Goals and Benefits

The project extends sidewalk from The Crossings at Pine Lake subdivision south to SE 24th Street where it will connect with existing soft pedestrian paths. Additionally, the narrow shoulders will be widened to accommodate bicycles.

Timeline

Construction planned for Summer/Fall 2016.

Budget

$650,000

Public Involvement

See the "Comments" tab at top, just above the summary.

Permits, Environmental Review

January 19, 2016 - JARPA application submitted to U.S. Army Corps of Engineers

February 12, 2016 - SEPA application submitted to Sammamish Community Development

News releases