| Public Meetings |
June - September 2007 |
| Park Commission Updates |
June 2007 - December 2008 |
| City Council Updates |
June 2007 - December 2008 |
| Master Plan Adoption |
September 2009 |
| Phase I Construction Documents |
Fall 2010 |
| Phase I Permitting |
Winter 2010/2011 |
| Phase I Bid |
Spring 2011 |
| Phase I Construction |
Summer 2011 |
| Park Opening |
Fall 2011 |
| On-Going Volunteer Work Parties and Partnerships |
January - December 2012 |
| Phase II Design and Construction Documents |
January - December 2013 |
| Phase II Permitting |
January - February 2014 |
| Phase II Bid (parking lot improvements) |
April 2014 |
| Phase II Construction |
April/May 2014 - August 2014 |
| Sahalee Parking Lot and Trail Connection Opening |
August 1, 2014 |