The City Council authorized funding to make minor intersection improvements such as turn pocket extensions and channelization modification to improve traffic flow and enhance driver experience. The Project would provide traffic operation improvements at the following five arterial intersections:
The project is currently under substantial completion.
June 21, 2018 - Design completed
June 25, 2018 - Advertised for bidding
July 10, 2018 - Bid opening
July 17, 2018 - Award project
July 27, 2018 - Pre-construction meeting
August 14, 2018 - Begin construction
May, 2019 - Project completed
estimated cost
$706,270