Overview

The City Council authorized funding to make minor intersection improvements such as turn pocket extensions and channelization modification to improve traffic flow and enhance driver experience. The project provided traffic operation improvements at five arterial intersections:

  • 228th Ave SE & SE 8th St
  • 228th Ave NE & NE 8th St
  • 228th Ave NE & NE 4th St
  • 228th Ave SE & Issaquah-Pine Lake Rd SE
  • 228th Ave SE & SE 20th St

The project is currently under substantial completion.

Project Timeline

June 21, 2018 - Design completed

June 25, 2018 - Advertised for bidding

July 10, 2018 - Bid opening

July 17, 2018 - Award project

July 27, 2018 - Pre-construction meeting

August 14, 2018 - Begin construction

May 2019 - Project completed