UPDATE: Louis Thompson Rd work finished early, E Lk Samm Pkwy to start Monday

Release Date: October 06, 2017

The ditch and culvert maintenance on Louis Thompson Road between 210th Pl. N.E. and 206th Ave. N.E. has completed ahead of schedule. Similar maintenance will commence earlier than previously scheduled along E. Lake Sammamish Pkwy.  The work on the parkway will begin this coming Monday, October 9th and continue through the end of the month, from Inglewood Hill Rd. and N.E. 49th Pl. This work will require intermittent one-way lane closures between 9 a.m. and 3 p.m., Monday through Friday. We expect traffic delays during some of the lane closures. We will complete work that does not involve lane closures between 8 a.m .and 4 p.m. 

For questions, please contact Associate Stormwater Engineer Danika Globokar at (425) 295-0516 or dglobokar@sammmamish.us.