Stormwater Retrofit Program
2027 Program
Locations
The current Retrofit Program will target the two highest priority projects identified by the Guidance Manual. The project goal is reconstructing the following two storm water facilities:
- Site 1: An existing stormwater vault located within the Demery Hill subdivision (sketch). The Guidance Manual identifies this as Retrofit Site #2131 on King County Parcel 95440-0530.
- Site 2: An existing stormwater pond located at the southeast corner of the intersection of SE 20th Street and 228th Avenue SE (sketch). The Guidance Manual identifies this as Retrofit Site #3000 on King County Parcel 042406-9131.
Project Map
Site 1: Demery Hill Vault Retrofit
The Demery Hill stormwater facility was built in the 1980s as part of the neighborhood’s drainage infrastructure. The existing vault provides approximately 42,000 cubic feet of detention storage but does not provide water quality treatment.
The project will install a new underground treatment vault to reduce phosphorus and suspended solids in stormwater runoff before it flows downstream toward Lake Sammamish. The improvements will supplement the existing detention facility, helping protect downstream water quality.
Construction is anticipated in summer 2027.
Site 2: 228th Pond Retrofit
This stormwater pond was built in 2001 as part of the 228th Avenue widening project. The existing facility provides limited detention storage and treats stormwater through a permanent pool and a media filter vault.
The project will improve water quality treatment by expanding the pond bottom to the north and modifying the pond’s interior slopes. Improvements also include replacing the perimeter fence and access gate. The revised design focuses on water quality treatment rather than increasing flow control storage.
These improvements will help reduce pollutants in stormwater runoff within the Pine Lake basin. Construction is anticipated in summer 2027.
Funding
The City’s adopted budget includes these projects within the Stormwater Capital Fund (438 Fund). The City is using funds allocated to Sammamish from the Sub-regional Opportunity Fund, managed by King County, to cover a portion of the design and construction costs. All remaining project costs are funded by Stormwater Utility ratepayers.
Design and Permitting
PACE Engineers, Inc. of Kirkland, Washington has completed the design for both projects. Required permits have been obtained.
Construction
Each project will be advertised separately for competitive bidding. Construction for both projects is anticipated in summer 2027.