Skip to the main content

Immigrant and Refugee Resources

Please click "learn more" to access resources. 

Learn more

Big Rock Park Improvements

A wooden footbridge at Big Rock Park North with railings crosses over a grassy area in a park; playground equipment and a fenced-off section are visible in the background.

Phase I construction at Big Rock Park North was completed in 2016. The new playground boasts many exciting features including:

  • a zipline;
  • hillside slide;
  • boulder climb;
  • earth mound tunnel;
  • log steppers; and
  • creative building blocks.

Eighteen parking spaces were added, as well as a park entrance, boardwalk, and plaza overlooking a newly restored meadow.

Documents

A grassy field with gentle hills, bordered by a white fence on the right. Tall evergreen trees and colorful autumn trees stand under a partly cloudy sky in Big Rock Park North.

Timeline

Design - Construction

Consultant Selection September 2014 - December 2014 
Schematic Design  December 2014 - February 2015 
Design Development  February 2015 - April 2015 
Construction Plans  April 2015 - May 2015
Permit Review  May 2015 - June 2015 
Bidding  July 2015 - August 2015 
Phase I Construction   September 2015 - December 2015 
Park Opening      January 2016