The Cone Zone: Scheduled Road Work in Sammamish Week of March 25 - 31

Release Date: March 24, 2023

the cone zone scheduled road work projects to know about - photos of orange road construction cones lined up on road

FOR WINTER WEATHER UPDATES, PLEASE VISIT THE CITY OF SAMMAMISH SNOW UPDATE.

 

228th Avenue Overlay

Construction Duration: March 2023 – June 2023 

Work to resurface 228th Avenue from SE 8th Street to NE 8th Street began Monday, March 6th. Work crews have begun making preparations for the pavement overlay. The typical hours for lane closure are 9:30am-3:00pm. There will be a pause in the work for the next two weeks to capture City Wide Traffic Counts. Work will begin again the week of March 27th. For more information please visit https://www.sammamish.us/projects/projects/pavement-management/228th-avenue-overlay/ 

 

2023 Citywide Traffic Counts

The City of Sammamish will be collecting traffic counts throughout the city on March 13-26. Tubes will be placed on main roadways to collect traffic volumes. These tubes will not impact traffic, however they may be felt when driving over them, drivers should not be alarmed. Also drivers should use caution when passing the contractor’s vehicles when stopped on the side of the road to place tubes or check on their equipment.

 

PSE Cable Remediation Program

Puget Sound Energy will be working in Sunny Hills Estates neighborhood at 255TH Ave SE & SE 31st Pl starting Monday March 20th through the middle of April, with working hours 7:00am – 5:00pm Monday through Thursday. This is a power cable remediation job that will have some traffic delays with traffic control present. All restoration will take place shortly after they are finished in April.

 

Louis Thompson Tightline Project – Potholing for Underground Utilities

Construction Duration: April 3 – April 10

Applied Professional Services will be potholing for buried utility services (PSE power and gas, Comcast, Ziply) that may conflict with designed road improvements from East Lake Sammamish Parkway up the hill to 210th Place SE. The work will take approximately 6 days. Utilities will be located with temporary paint prior to work, and traffic will be limited to single lane for vactor truck and crew.

 

East Lake Sammamish Trail South Segment B Stage 2 Construction

This is a King County Trail Project 

The King County East Lake Sammamish Trail (ELST) South Segment B Phase 2 began construction in Spring 2022. All private property owners adjacent to the trail will be able to access their property during construction with limited exceptions for safety reasons. For example, access may be limited, or neighbors may experience short delays during major material unloading or wall construction along a lane. King County plans to incorporate flaggers/spotters on site on site to help pedestrians safely access their properties during daytime.

  • Project Start Point: Approximately 1,350’ south of the intersection of SE 8thStreet / East Lake Sammamish Parkway SE (STA 371+59)
  • Project End Point: Approximately 750’ south of the intersection of NE 16thStreet / East Lake Sammamish Parkway SE (STA 468+00)

The last uncompleted ELST section, the 1.9-miles from Pine Lake Creek to Inglewood Hill Road, will be closed for construction beginning in early June 2022 until December 2023.

For additional project information, please visit the project website:  www.kingcounty.gov/eastlakesammamishtrail. You may also contact the project team directly by email at ELST@kingcounty.gov or by calling the project hotline at 1-888-668-4886.

 

East Lake Sammamish Trail South Segment B Stage 1 Construction

The King County East Lake Sammamish Trail (ELST) South Segment B Phase 1 continues with construction. There will be traffic impacts related to the closure of the gravel surface trail segment which causes the re-routing of cyclists and pedestrians to East Lake Sammamish Parkway (ELSP). Additionally, there will be construction traffic on ELSP.

  • Project Start Point: Intersection of SE 33rd/ East Lake Sammamish Shore Lane Drive SE
  • Project End Point: Approximately 900' south of the intersection of SE 8thStreet / East Lake Sammamish Parkway SE

 

Notices for construction activity outside of the City of Sammamish:

 

Road maintenance on 244th Ave NE near Redmond Fall City Rd, (SR-202)

This is a King County Local Services project.

King County Road Services Division is prioritizing 244th Ave NE near SR-202 to receive snow and ice pre-treatment. Due to a slide occurring in winter 2020, both lanes of 244th Ave NE are narrowed until the impacted support wall can be repaired. The repair of the support wall is expected to begin in Summer 2024. Soil samples yielded unexpected data, which caused the design phase to be extended. King County Road Services Division has a 24/7 Road Helpline - (206) 477-8100. More information on this project can be found, linked here.

 

Downtown Redmond Link Extension (DRLE) - Sound Transit work

This is a City of Redmond and Sound Transit project.

To stay up-to-date and learn more about this project, please visit the DRLE tab.